| Pre-turnaround | Weeks -4 to -1 | Depressurize, bleed-down, atmosphere testing, induction, and site setup. | Preparation controls |
| Execution start | Week 1 | Scaffolding, initial hot work, and first confined-space packages. | PTW: Hot Work, CSE, Work at Height |
| Mid-execution | Weeks 2-3 | Catalyst unloading, exchanger weld repair, and seal replacement. | PTW: Hot Work, CSE, LOTO |
| Late execution | Weeks 4-5 | Welding continuation, coatings, and pressure-vessel reassembly. | PTW: Hot Work, Work at Height |
| Testing and commissioning | Weeks 6-7 | Hydrostatic/pressure testing and system validation. | Test and safety protocols |
| Return to operations | Week 8 | Controlled re-pressurization and production ramp-up. | Operational handover authorization |